Project planning: new building hot dip coating line


Construction phases hot dip coating line

A production complex with a length of 370 m, maximum approx. 90 m width and maximum approx. 67 m high.

Order size: approx. 7,400 t steel structure workshop planning incl. connection static calculations.


 
11.06.2020 Project preview: New Beiersdorf Campus

This construction project involves the expansion / new construction of the Beiersdorf Group headquarters in Hamburg. IMC has received an order from... 


12.08.2019 New project started: VW Wolfsburg power plant

At the end of July a new IMC project for steel construction planning of a stage in the VW Wolfsburg power plant started. For approx. 190t steel... 


08.07.2019 Project start ACPS Ingersheim, production hall

In the Ingersheim industrial area, ACPS Automotive GmbH will build its new headquarters and development center. The range of services IMC...