IMC has been a competent and reliable partner in planning and development of mobile sites for several years.

Frank E., Director of Building Technology – Mobile phone group

Filter system Saal Germany (DE)

Set up of a filter system in an existing reinforced concrete structure. The fitting process was extremely complicated since it had to take place in full operating mode, no inventory documents were available and the fitting had to take place in an 80-year old reinforced concrete structure, under which multi-track railway operations were running. 

Project data
City: Saal a.d. Donau Germany (DE)
 
Implementation: 2006
 
Services: General Contractor
General Planner
 

Continue to:
previous project
next project
Project map
Project list

More projects

Hall expansion ArcelorMittal

Implementation: 2007
Services: Consulting
Erection Planning
General Contractor
General Planner
Shop Drawings
Structural Design / Static

[Show project]

Open-cast mining equipment Australia (AU)

Implementation: 2008
Services: Shop Drawings

EOA Project - Chile (CL)

Implementation: 2008
Services: Shop Drawings
 


03.09.2017 Renewed Salt Conveyance Site working

IMC obtained an order for planning a new structural steel conveyor bridge at the plant Werra (site Wintershall) of the K+S enterprise in Heringen....[mehr]


21.08.2017 The Get-Together 2017. An IMC Tradition.