Project data
City: Leipzig Seehausen (DE)
 
Implementation: 2011
 
Services: Generálny dodávateľ
Generálny projektant
 

Continue to:
previous project
next project
Project map
Project list

More projects

Kraftwerk Boxberg

Implementation: 2008
Services: Shop Drawings
Structural Design / Static

[Show project]

Mining Equipment Chile (CL)

Implementation: 2008
Services: Shop Drawings
Structural Design / Static

[Show project]

Mining Equipment Chile (CL)

Implementation: 2014
Services: Shop Drawings
Structural Design / Static

[Show project]

 



03.09.2017 Renewed Salt Conveyance Site working

IMC obtained an order for planning a new structural steel conveyor bridge at the plant Werra (site Wintershall) of the K+S enterprise in Heringen....[mehr]